Type
Roadway Improvements
Project number
1082
Council Districts
01, 03, 05, 06, 09

Scope

Includes paving of unpaved portions of Braeburn Rd, Main St, and Hirsch St.

Paid

Project Start

Mar 2016

Design Finish

Dec 2019

Construction Start

Feb 2024

Construction Finish

Jul 2025
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Not Started
Engineering/Design
Planning & Development
Procurement
Design
Construction
Construction
Closeout
Closeout

Additional Project Information