Wieuca Rd Roundabout

Roadway Improvements

Type

Roadway Improvements

Project Number

1085

Council Districts

07

Scope

Installation of a two-lane roundabout for roadway and mobility improvements — including pedestrian and bicycle safety — on Wieuca Rd at the intersection with Phipps Blvd and Park Ave. Improvements will include roadway reconfiguration, pedestrian improvements, and bicycle side-path along Wieuca Rd from Peachtree Rd to Old Ivy Rd. The proposed project also includes a new traffic signal system at the intersection of Old Ivy Rd and Wieuca Rd. Additional work incudes utility relocation, drainage design, resurfacing, landscaping, and signage.

Current Budget

$5,569,980.00

Paid

$2969344.23
Project Start
2015-11-01

Anticipated Design Finish

2023-11-28

Construction Start

2024-05-08
Construction Finish
2026-05-30

Disclaimer: Project schedules and scopes are subject to change.