Ford Street NW from Spring Avenue NW to the Dead End Howell Mill Road from Trabert Avenue NW to Huff Road NW 10th Street NE from Piedmont Avenue NE to Monroe Drive NE Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE

Safe Streets

Westside Beltline Connector Sidewalks

Sidewalks

Type

Sidewalks

Project Number

3064

Council Districts

03

Scope

The Westside Beltline Sidewalk Connector Project will replace approximately 2 miles of sidewalk within ¼ mile of the Westside Beltline Connector trail along various streets. The streets to be addressed are Cameron Alexander Blvd between Griffin St and Northside Drive, Griffin Street, Sunset Ave and Walnut St., Jett St. between Griffin St and Vine Street, and other small segments.

Current Budget

$2,103,560.80

Paid

$0.00
Project Start
2023-08-11

Anticipated Design Finish

2025-12-19

Construction Start

2026-05-13
Construction Finish
2027-01-23

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.