West Peachtree St NE/NW

Resurfacing

Type

Resurfacing

Project Number

5006

Council Districts

2, 3, & 4

Scope

AURA Bond-World Cup Prep Resurfacing; Group 05 – Peachtree St. 11th Street.

Current Budget

$5,143,953.45

Paid

$0.00
Project Start
2024-08-26

Anticipated Design Finish

2025-08-26

Construction Start

2026-03-03
Construction Finish
2026-05-30

Disclaimer: Project schedules and scopes are subject to change.