Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW

Safe Streets

West Lake Ave Bridge Replacement

Bridges

Type

Bridges

Project Number

1026

Council Districts

03, 04

Scope

Bridge replacement over CSX and MARTA tracks near I-20 and Martin Luther King (MLK) Jr Dr. Design includes sidewalk and shared-use path.

Current Budget

$3,871,620.19

Paid

$1264493.38
Project Start
2017-04-10

Anticipated Design Finish

2027-03-26

Construction Start

2027-12-30
Construction Finish
2030-01-18

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.