Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE Colmer Avenue SE from Moreland Avenue SE to Mortimer Street SE North Avenue NE from Oakdale Road NE to Candler Park Drive NE Tuxedo Road NW from Northside Drive NW to West Paces Ferry Road NW FIFA Fan Festival Road Closures and Delivery

Safe Streets

Traffic Signals

Signals

Type

Signals

Project Number

4038

Council Districts

Citywide

Scope

Signal equipment upgrades, signal retiming, and reconfiguration as determined necessary at various locations citywide.

Current Budget

$7,060,235.02

Paid

$231391.39
Project Start
2024-04-08

Anticipated Design Finish

2026-09-13

Construction Start

2026-11-06
Construction Finish
2027-07-03

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout