Ford Street NW from Spring Avenue NW to the Dead End Howell Mill Road from Trabert Avenue NW to Huff Road NW 10th Street NE from Piedmont Avenue NE to Monroe Drive NE Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE

Safe Streets

Traffic Combo 2

Signals

Type

Signals

Project Number

1069

Council Districts

01, 02, 04, 05

Scope

Will include fiber installation, minor signal upgrades, installation of bicycle signs, and signal removals on several corridors, signal cabinet upgrades, vehicle detection, ADA ramps, and pedestrian push-button upgrades. Corridors include R D Abernathy Blvd/Georgia Ave, Atlanta Ave, Hosea Williams Dr, Boulevard, McDaniels St, and Glenwood Ave. Atlanta Ave includes signage to support one-way to two-way conversion.

Current Budget

$3,050,231.51

Paid

$1008805.18
Project Start
2016-04-18

Anticipated Design Finish

2027-11-29

Construction Start

2028-06-10
Construction Finish
2029-05-05

Disclaimer: Project schedules and scopes are subject to change.