Safe Streets

Traffic Combo 1

Archive

Type

Archive

Project Number

1068

Council Districts

01, 11, 12

Scope

Phase 1 Includes signal upgrades, pedestrian signal upgrades, ADA ramps, striping, intersection upgrades, detection, and signal timing coordination at the following: Claire Dr at 3 locations; Lakewood Ave at 3 locations; Sylvan Rd at 2 locations; and Cleveland Ave at 9 locations. Phase 2 includes signal improvements on Sylvan Rd at 2 locations and Greenbriar Pkwy at 5 locations. Signal Timing has been added to the Design and Construction contract.

Current Budget

$4,587,350.38

Paid

$4383131.66
Project Start
2016-04-18

Anticipated Design Finish

2021-01-29

Construction Start

2023-09-15
Construction Finish
2025-06-03

Disclaimer: Project schedules and scopes are subject to change.