McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW

Safe Streets

Traffic Combo 1 – Phase 2

Signals

Type

Signals

Project Number

1138

Council Districts

11, 12

Scope

Phase 2 includes signal improvements on Sylvan Rd at 2 locations and Greenbriar Pkwy at 5 locations. Signal Timing has been added to the Design and Construction contract.

Current Budget

$670,887.35

Paid

$102083.50
Project Start
2017-04-30
Anticipated Design Finish
2030-04-03

Construction Start

2030-10-30
Construction Finish
2032-10-19

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.