Type

Safe Streets

Project Number

4073

Council Districts

Citywide

Scope

Installation of strategic traffic calming infrastructure at high ROI locations citywide.

Current Budget

$10,188,493.82

Paid

$1000000.00
Project Start
2024-04-08

Anticipated Design Finish

2026-12-12

Construction Start

2027-03-13
Construction Finish
2028-12-01