Spring Street Bridge Phase 2

Archive

Type

Archive

Project Number

3006

Council Districts

04

Scope

Includes demolition and reconstruction of the viaduct and roadway from the Mitchell St intersection between the Richard B. Russell Federal Building and the MLK Jr. Building to the MLK Jr. Dr intersection, widening of the new MLK Jr. Dr viaduct construction from the new abutment to the Spring St viaduct, and widening of the approach slab, construction of a retaining wall, and reconstruction of lower MLK Jr. Dr.

Current Budget

$30,194,151.69

Paid

$22986430.07
Project Start
2017-03-01

Anticipated Design Finish

2018-03-01

Construction Start

2018-07-16
Construction Finish
2025-07-08

Disclaimer: Project schedules and scopes are subject to change.