Scope

The Silver Comet Connector MacArthur Blvd NW Segment project (“MacArthur”) follows MacArthur
Blvd approximately 0.4 miles from Chattahoochee Ave NW to the existing Whetstone Trail. The trail will provide the community with a safe way to walk or bike from Chattahoochee Ave to the Whetstone Trail, and, when complete, will be a vital segment of bringing the Silver Comet into Downtown Atlanta. The trail will be a 10-foot-wide concrete side path and will stay in the right-of-way.

Current Budget

$250,000.00

Paid

$250000.00
Project Start
2023-04-04

Anticipated Design Finish

2023-12-12

Construction Start

2025-02-21
Construction Finish
2025-10-10

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.