McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW

Safe Streets

Routine Maintenance of Transportation Assets in the City of Atlanta

Roadway Improvements

Type

Roadway Improvements

Project Number

3087

Council Districts

All

Scope

The selected contractor shall furnish all labor, materials, equipment, and supervision necessary to perform routine maintenance work on various transportation assets within the City, including street signs, lane markings, asphalt and concrete surfaces, gravel road grading, traffic signal components, and pre-construction inspections.

Current Budget

$4,095,993.60

Paid

$438714.20
Project Start
2025-07-22
Anticipated Design Finish

Construction Start

2024-05-13
Construction Finish
2026-06-01

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout