McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW

Safe Streets

Proctor Creek Greenway – Phase 1

Archive

Type

Archive

Project Number

1040

Council Districts

09

Scope

Two (2) miles of shared-use path from Bankhead MARTA Station to existing West Highlands Trail and connecting to the Westside Quarry Park.

Current Budget

$3,348,826.54

Paid

$3348826.54
Project Start
2015-07-05
Anticipated Design Finish

Construction Start

2017-07-31
Construction Finish
2019-01-15

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.