Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW

Safe Streets

Piedmont Ave Signals

Archive

Type

Archive

Project Number

1060

Council Districts

01, 02, 04, 05, 06

Scope

Includes cabinet upgrades and fiber communications to all traffic signals, and a mast arm pole replacement at the Piedmont Ave/Decatur St intersection.

Current Budget

$764,821.73

Paid

$764821.73
Project Start
2016-08-26

Anticipated Design Finish

2017-05-31

Construction Start

2018-01-22
Construction Finish
2021-01-29

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.