Type
Sidewalks
Project number
1061
Council Districts
01, 02, 05

Scope

[Includes a bicycle lane from MLK Jr Dr to North Ave and pedestrian crosswalks with Rectangular Rapid Flashing Beacons (RRFB) at the Linden Ave, Armstrong Place, and Renaissance Pkwy intersections, and drainage improvements. On-street parking will also be added as part of the project.] SOW aligned with MAF Proj# 4001 as follows: Installation of on-street dedicated transit lanes on Courtland St and protected bike lanes on Piedmont Ave and other safety improvements where feasible ( e.g. ADA improvements, vertical lane delineators/safe crossing treatments, lane narrowing, etc.).

Paid

Project Start

May 2023

Design Finish

Jun 2025

Construction Start

Sep 2025

Construction Finish

Nov 2027
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout

Additional Project Information