Type
Sidewalks
Project number
1061
Council Districts
01, 02, 05

Scope

[Includes a bicycle lane from MLK Jr Dr to North Ave and pedestrian crosswalks with Rectangular Rapid Flashing Beacons (RRFB) at the Linden Ave, Armstrong Place, and Renaissance Pkwy intersections, and drainage improvements. On-street parking will also be added as part of the project.] SOW aligned with MAF Proj# 4001 as follows: Installation of on-street dedicated transit lanes on Courtland St and protected bike lanes on Piedmont Ave and other safety improvements where feasible ( e.g. ADA improvements, vertical lane delineators/safe crossing treatments, lane narrowing, etc.).

Paid

Project Start

Jan 2017

Design Finish

Oct 2020

Construction Start

Construction Finish

Feb 2025
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete