Piedmont Ave Complete Street

Type
Project number
1015
Council Districts
02, 06

Scope

Includes road resurfacing, sidewalk and curb improvements, a protected bicycle lane, and landscaping from Ponce De Leon Ave to 15th St.

Paid

Project Start

Aug 2017

Design Finish

Construction Start

Aug 2024

Construction Finish

May 2026
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete