Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE Colmer Avenue SE from Moreland Avenue SE to Mortimer Street SE North Avenue NE from Oakdale Road NE to Candler Park Drive NE Tuxedo Road NW from Northside Drive NW to West Paces Ferry Road NW FIFA Fan Festival Road Closures and Delivery

Safe Streets

Pearl Street Traffic Calming

Archive

Type

Archive

Project Number

3069

Council Districts

05

Scope

Pearl Street traffic calming project consists of demolition and removal of existing asphalt pavement approximately 12-inch deep to install proposed concrete raised crosswalk at mid-block. Project includes installation of a speed table on the approach and one on the trailing side of the raised crosswalk. The project will also replace broken brick paver sidewalks in the immediate vicinity of the raised crosswalk, installation of traffic signs, striping, granite curbing, curb ramp for ADA compliance and provisions for drainage. The project is located on Pearl Street between SR154/ Memorial Drive and Gaskill Street in Atlanta Council District 5.

Current Budget

$199,251.18

Paid

$199251.18
Project Start
2024-05-31

Anticipated Design Finish

Construction Start

2025-03-26
Construction Finish
2025-04-28

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.