Scope

Construction of a12′ hard-surface multi-use path connecting the existing Peachtree Creek Greenway to the Cheshire Farm Trail.

Current Budget

$10,000,000.00

Paid

$0.00
Project Start
2020-07-23

Anticipated Design Finish

2027-01-05

Construction Start

2027-04-06
Construction Finish
2028-03-30