Peachtree Center Ave

Archive

Type

Archive

Project Number

5017

Council Districts

1

Scope

AURA Bond-World Cup Prep Resurfacing; Group 01 – Edgewood Ave NE to Peachtree St. Preparing roadway for resurfacing activities; activity will start by June 18, 2025.

Current Budget

$1,418,553.05

Paid

$1026803.69
Project Start
2024-08-26

Anticipated Design Finish

2024-12-06

Construction Start

2025-06-03
Construction Finish
2025-08-02

Disclaimer: Project schedules and scopes are subject to change.