Ford Street NW from Spring Avenue NW to the Dead End Howell Mill Road from Trabert Avenue NW to Huff Road NW 10th Street NE from Piedmont Avenue NE to Monroe Drive NE Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE

Safe Streets

PATH SW Beltline Connector Trail

Multipurpose Trails

Type

Multipurpose Trails

Project Number

4072

Council Districts

11

Scope

On-Street trail between southwest Atlanta neighborhoods and the Atlanta BeltLine Westside Trail and connecting to the Lionel Hampton trail on the west end.

Current Budget

$1,000,000.00

Paid

$0.00
Project Start
2024-04-08

Anticipated Design Finish

Construction Start

Construction Finish

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout