Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW

Safe Streets

PATH 400

Multipurpose Trails

Type

Multipurpose Trails

Project Number

1038

Council Districts

06, 07

Scope

Includes the expansion of the PATH 400 shared-use path along SR 400 from Wieuca Rd to Loridans Dr, Loridans Dr to City Limits, and new segments within Peachtree Rd to Garson Dr.

Current Budget

$21,201,178.76

Paid

$16400486.17
Project Start
2018-12-06

Anticipated Design Finish

2023-09-05

Construction Start

2023-02-13
Construction Finish
2027-04-09

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout