Scope

Includes the expansion of the PATH 400 shared-use path along SR 400 from Wieuca Rd to Loridans Dr, Loridans Dr to City Limits, and new segments within Peachtree Rd to Garson Dr.

Current Budget

$21,201,178.76

Paid

$16400486.17
Project Start
2018-12-06

Anticipated Design Finish

2023-09-05

Construction Start

2023-02-13
Construction Finish
2027-04-09