Oakdale Rd Sidewalk Installation

Sidewalks

Type

Sidewalks

Project Number

4123

Council Districts

2,6

Scope

Sidewalk installations to address missing segments along the corridor as identified by ATLDOT’s Safety, Equity, and Mobility analysis.

Current Budget

$139,906.00

Paid

$0.00
Project Start
2026-01-31

Anticipated Design Finish

NA

Construction Start

2026-03-26
Construction Finish
2026-11-06

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout