Scope

Pedestrian improvements on North Highland Ave from Alaska Ave to Elizabeth St, including installation of mid-block crossings, a new dedicated westbound bicycle lane and a protected pedestrian crossing with Rectangular Rapid Flashing Beacon (RRFB) at the Inman Village Pkwy intersection. Roadway pavement markings with on-street parking and designated passenger pickup/drop-off areas also are proposed along the project limits.

Current Budget

$516,506.38

Paid

$281894.80
Project Start
2017-01-09

Anticipated Design Finish

2019-09-19

Construction Start

2025-09-11
Construction Finish
2026-09-11

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.

Scroll to Top