New Hope Road Sidewalk Improvement

Sidewalks

Type

Sidewalks

Project Number

3076

Council Districts

11

Scope

Construction of new sidewalk, concrete curbing, drainage structures, traffic signs and pavement striping along the west side of New Hope Road SW beginning from Gilford Forest Drive, SW to approximately 250 feet south of Brightwood Lane SW. This will provide pedestrian safety and connectivity.

Current Budget

$130,000.00

Paid

$0.00
Project Start
2025-01-13

Anticipated Design Finish

Construction Start

2025-01-13
Construction Finish
2026-08-26