Nelson St

Resurfacing

Type

Resurfacing

Project Number

5020

Council Districts

3 & 4

Scope

AURA Bond-World Cup Prep Resurfacing; Group 02 – Northside Dr to Forsyth St SW

Current Budget

$500,000.00

Paid

$42211.00
Project Start
2024-08-26

Anticipated Design Finish

2025-03-05

Construction Start

2025-08-04
Construction Finish
2025-10-03

Disclaimer: Project schedules and scopes are subject to change.