Safe Streets

Mt Paran Rd Resurfacing & Safety Improvements

Archive

Type

Archive

Project Number

4066

Council Districts

8

Scope

Complete resurfacing of the identified extents combined with safety improvements and interventions where feasible (e.g. vertical lane delineators/safe crossing treatments, lane narrowing, etc.)

*Project should be considered for (in-house) safety improvements such as mid-block crossings or other intersection related striping improvements.

Current Budget

$3,500,000.00

Paid

$3023361.97
Project Start
2024-02-05

Anticipated Design Finish

NA

Construction Start

2024-04-01
Construction Finish
2024-11-26

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.