Moores Mill Rd @ W. Wesley Rd Intersection Improvements

Type
Signals
Project number
1055
Council Districts
08

Scope

Includes improvements to relieve congestion at the Moores Mill Rd/W. Wesley Rd intersection.

Paid

Project Start

Jan 2016

Design Finish

Construction Start

Construction Finish

Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete

Additional Project Information