Type
Complete Street
Project number
1012
Council Districts
01, 02, 05, 06

Scope

Includes resurfacing and pedestrian improvements between 10th St and Woodward Ave. Signal improvements at intersections include replacement of traffic signal LEDs, cabinets, controller monitors, signal wiring, communications, and signal timing. Considerations for bicycles throughout to be included throughout.

Paid

Project Start

May 2016

Design Finish

Jun 2024

Construction Start

Jul 2024

Construction Finish

Oct 2026
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning & Development
Planning & Development
Design
Design
Construction
Construction
Complete
Complete

Additional Project Information