Type
Safe Streets
Project number
1012
Council Districts
01, 02, 05, 06

Scope

Includes resurfacing and pedestrian improvements between 10th St and Woodward Ave. Signal improvements at intersections include replacement of traffic signal LEDs, cabinets, controller monitors, signal wiring, communications, and signal timing. Considerations for bicycles throughout to be included throughout.

Paid

Project Start

May 2016

Design Finish

Mar 2027

Construction Start

Aug 2027

Construction Finish

Nov 2029
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout