Ford Street NW from Spring Avenue NW to the Dead End Howell Mill Road from Trabert Avenue NW to Huff Road NW 10th Street NE from Piedmont Avenue NE to Monroe Drive NE Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE

Safe Streets

MLK Jr. Dr Complete Street

Archive

Type

Archive

Project Number

1011

Council Districts

03, 04, 10

Scope

Includes pedestrian, signal, and lighting safety improvements; protected bicycle infrastructure; resurfacing; restriping; linear park; landscaping; art installations; and several bicycle infrastructure additions and improvements from Northside Dr to Fulton Industrial Blvd.

Current Budget

$16,476,898.87

Paid

$16079189.14
Project Start
2017-05-15

Anticipated Design Finish

2018-06-29

Construction Start

2018-06-30
Construction Finish
2021-06-29

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.