Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW

Safe Streets

Midtown Atlanta Regional Activity Center

Archive

Type

Archive

Project Number

3011

Council Districts

02,06

Scope

Enhances existing street intersections to improve pedestrian mobility, safety, and connectivity from MARTA stations and numerous local, regional, and express bus stops within Midtown Core Boundary of the Midtown Community Improvement District (MCID).

Current Budget

$1,421,600.00

Paid

$1421600.00
Project Start
2016-12-16

Anticipated Design Finish

2022-11-15

Construction Start

2023-03-13
Construction Finish
2024-07-05

Disclaimer: Project schedules and scopes are subject to change.