Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE Colmer Avenue SE from Moreland Avenue SE to Mortimer Street SE North Avenue NE from Oakdale Road NE to Candler Park Drive NE Tuxedo Road NW from Northside Drive NW to West Paces Ferry Road NW FIFA Fan Festival Road Closures and Delivery

Safe Streets

Midtown Atlanta Regional Activity Center

Archive

Type

Archive

Project Number

3011

Council Districts

02,06

Scope

Enhances existing street intersections to improve pedestrian mobility, safety, and connectivity from MARTA stations and numerous local, regional, and express bus stops within Midtown Core Boundary of the Midtown Community Improvement District (MCID).

Current Budget

$1,421,600.00

Paid

$1421600.00
Project Start
2016-12-16

Anticipated Design Finish

2022-11-15

Construction Start

2023-03-13
Construction Finish
2024-07-05

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout