Marietta Rd Bridge Replacement

Bridges

Type

Bridges

Project Number

4040

Council Districts

9

Scope

Full replacement of the distressed and weight-limited bridge on Marietta Road over the CSX Tracks just South of Thomas St NW
GDOT PI: 0019776
Legislation: 22-R-4179

Current Budget

$13,095,000.00

Paid

$0.00
Project Start
2024-04-08

Anticipated Design Finish

2028-01-20

Construction Start

2028-04-20
Construction Finish
2030-06-28

Disclaimer: Project schedules and scopes are subject to change.