Scope

Sidewalk installations to address missing segments along the corridor as identified by ATLDOT’s Safety, Equity, and Mobility analysis.

Current Budget

$1,915,782.00

Paid

$0.00
Project Start
2025-01-28

Anticipated Design Finish

2027-07-18

Construction Start

2027-10-17
Construction Finish
2029-01-13