Home » MAF – Dekalb Ave Complete Street
MAF – Dekalb Ave Complete Street

Type
Safe Streets
Project Number
1003
Council Districts
01, 02, 05
Scope
DESIGN ONLY. This project design will focus on improving mobility, operations, and safety along the 4.7-mile corridor of Decatur St/Dekalb Ave from Peachtree St to Ridgecrest Rd. Improvements to include bicycle, pedestrian, transit, and vehicular enhancements, with a continuous separated bicycle/shared-use facility on Dekalb Ave from Peachtree St in downtown Atlanta to the existing shared-use path at Rocky Ford Rd. The design also will correct ADA accessibility issues and improve intersection safety for pedestrians.
Current Budget
$2,972,279.05
Paid
$1396862.34
Project Start
2016-02-18
Anticipated Design Finish
2027-08-09
Construction Start
2028-01-07
Construction Finish
2028-12-06
Disclaimer: Project schedules and scopes are subject to change.
Phase
- Not Started
- Planning/Scoping
- Engineering/Design
- Procurement
- Construction
- Closeout
Additional Project Information
- Renew ATL Dekalb Avenue Public Meeting Information 11-2017
- De Kalb Avenue Public Meeting 3 Welcome Letter 04-18-18
- Dekalb Ave Corridor Improvements Fact Sheet Inman Park Community Meeting 02-15-17
- Dekalb Avenue 2-27-20 Roll Plot 2
- Dekalb Avenue 2-27-20 Roll Plot 1
- Dekalb Avenue Boards for Public Meeting 2-27-20 Typical Sections v4
- Dekalb Avenue Boards for Public Meeting 2-27-20
Phase
- Not Started
- Planning/Scoping
- Engineering/Design
- Procurement
- Construction
- Closeout