Macon Dr @ Old Hapeville Rd & Bromack Dr

Signals

Type

Signals

Project Number

1052

Council Districts

12

Scope

Includes the conversion of a traffic signal to an all-way stop.

Current Budget

$216,719.30

Paid

$36986.00
Project Start
2016-04-18

Anticipated Design Finish

2021-08-06

Construction Start

2025-09-11
Construction Finish
2026-09-11

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout