Ford Street NW from Spring Avenue NW to the Dead End Howell Mill Road from Trabert Avenue NW to Huff Road NW 10th Street NE from Piedmont Avenue NE to Monroe Drive NE Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE

Safe Streets

Little 5 Points CID Improvements

Sidewalks

Type

Sidewalks

Project Number

1099

Council Districts

02

Scope

Includes the construction of a new pedestrian place comprised of sidewalk and ADA ramps, pedestrian furniture, bicycle racks, redesigned tree wells, and additional landscaping of 0.1 acres at the intersection of Moreland, Euclid, and McLendon Avenues. Other improvements include stormwater infrastructure replacement, utility relocation, and pedestrian lighting.

Current Budget

$658,913.11

Paid

$658913.11
Project Start
2018-04-24

Anticipated Design Finish

2019-12-05

Construction Start

2025-07-17
Construction Finish
2026-03-20

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout