John Portman Boulevard (Harris St) Resurfacing

Archive

Type

Archive

Project Number

1028

Council Districts

02, 04, 05

Scope

Includes the resurfacing of John Portman Blvd from Centennial Olympic Park Dr to Piedmont Ave.

Current Budget

$223,000.00

Paid

$223000.00
Project Start

Anticipated Design Finish

2016-09-25

Construction Start

2016-10-01
Construction Finish
2016-11-30

Disclaimer: Project schedules and scopes are subject to change.