Ford Street NW from Spring Avenue NW to the Dead End Howell Mill Road from Trabert Avenue NW to Huff Road NW 10th Street NE from Piedmont Avenue NE to Monroe Drive NE Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE

Safe Streets

Inman Park Neighborhood Improvements

Archive

Type

Archive

Project Number

1075

Council Districts

02

Scope

Includes improvements at the Edgewood Ave/Euclid Ave intersection and pedestrian improvements at the Irwin St/Lake Ave at Krog St intersection.

Current Budget

$361,360.07

Paid

$361360.07
Project Start
2016-11-09

Anticipated Design Finish

2020-01-07

Construction Start

2022-04-25
Construction Finish
2024-03-29

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout