Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW

Safe Streets

Inman Park Neighborhood Improvements

Archive

Type

Archive

Project Number

1075

Council Districts

02

Scope

Includes improvements at the Edgewood Ave/Euclid Ave intersection and pedestrian improvements at the Irwin St/Lake Ave at Krog St intersection.

Current Budget

$361,360.07

Paid

$361360.07
Project Start
2016-11-09

Anticipated Design Finish

2020-01-07

Construction Start

2022-04-25
Construction Finish
2024-03-29

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.

Scroll to Top