Type
Roadway Improvements
Project number
3022
Council Districts
9

Scope

Widening of Huff Road from two (2) lanes to three (3) lanes by adding a center turn lane from Howell Mill Rd to just west of Earnest St.

Paid

Project Start

Apr 2017

Design Finish

Feb 2024

Construction Start

Oct 2024

Construction Finish

Feb 2026
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning & Development
Planning & Development
Design
Design
Construction
Construction
Complete
Complete

Additional Project Information