Hightower Rd Sidewalk Installation

Archive

Type

Archive

Project Number

4112

Council Districts

9

Scope

Sidewalk installations to address missing segments along the corridor as identified by ATLDOT’s Safety, Equity, and Mobility analysis.

Current Budget

$505,481.00

Paid

$272142.00
Project Start
2025-01-28

Anticipated Design Finish

NA

Construction Start

2025-05-01
Construction Finish
2025-07-31

Disclaimer: Project schedules and scopes are subject to change.