Safe Streets

Glenwood and Moreland Intersection

Archive

Type

Archive

Project Number

1074

Council Districts

01, 05

Scope

Includes the right-of-way acquisition for the realignment of SR 260/Glenwood Ave to the south to eliminate the approximate 70-foot offset that currently exists as it crosses US 23/SR 42/Moreland Ave. The realignment will accommodate two vehicular lanes and extend two bicycle lanes along Glenwood Ave through the Moreland Ave intersection. Glenwood Ave also will be restriped to accommodate a left-turn lane on the eastern leg of the intersection.

Current Budget

$342,998.98

Paid

$342998.98
Project Start
2015-11-30

Anticipated Design Finish

2018-04-19

Construction Start

2018-01-15
Construction Finish
2019-07-15

Disclaimer: Project schedules and scopes are subject to change.