Scope

Installation of sidewalks where needed to provide contiguous sidewalk coverage on both sides of the roadway, and construction of a connection to the Southside BeltLine Trail at the eastern extent of the corridor.

Current Budget

$873,000.00

Paid

$0.00
Project Start
2024-03-01

Anticipated Design Finish

2027-03-03

Construction Start

2027-06-02
Construction Finish
2028-05-26

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout