Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE Colmer Avenue SE from Moreland Avenue SE to Mortimer Street SE North Avenue NE from Oakdale Road NE to Candler Park Drive NE Tuxedo Road NW from Northside Drive NW to West Paces Ferry Road NW FIFA Fan Festival Road Closures and Delivery

Safe Streets

Eastside Trolley Greenway Trail

Archive

Type

Archive

Project Number

1037

Council Districts

05

Scope

Includes the expansion of the Eastside Trolley Trail and shared-use path through the Reynoldstown, Edgewood, and Kirkwood neighborhoods from Stovall St to Arizona Ave.

Current Budget

$1,880,827.77

Paid

$1880827.77
Project Start
2019-09-30

Anticipated Design Finish

2023-10-22

Construction Start

2022-07-11
Construction Finish
2023-10-19

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.

Scroll to Top