Scope

Design and construct the following: 1) Wayfind Signage: $3M for improvements to pedestrian routing and way finding downtown; street activations to support pedestrian and multimodal activity. 2) Lighting: $4M for installation of up to 150 new streetlights. 3) Resurfacing: $62M for approximately 27 centerline miles of streets with PCI less than 50. 4) Restriping: $4M for 200 intersection crosswalks and lane markings for corridors with PCI greater than 50, to include safer streets and redesigns. 5) Sidewalk and ADA Ramps: $5M for 2.89 miles of sidewalk rated poor and very poor, and 82 ADA ramps.

Current Budget

$-

Paid

$0.00
Project Start
2024-08-26

Anticipated Design Finish

Construction Start

2025-06-03
Construction Finish
2026-05-30

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout
Scroll to Top