Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW

Safe Streets

Dekalb Ave Safety Improvements

Archive

Type

Archive

Project Number

1073

Council Districts

02, 05

Scope

Includes traffic signal coordination upgrades, intersection improvements, resurfacing, and bicycle lane installations on Dekalb Ave from Jackson St to Ridgecrest Rd, and removal of the reversible lane from Jackson St to Oxford Pl. Bicycle lanes are included as part of the Mayor’s Action Plan for Safer Streets (APSS) Across Atlanta.

Current Budget

$11,502,730.11

Paid

$9783143.57
Project Start
2016-02-29

Anticipated Design Finish

2020-08-20

Construction Start

2021-08-27
Construction Finish
2023-12-31

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout