Safe Streets

Courtland St NE/SE

Resurfacing

Type

Resurfacing

Project Number

5009

Council Districts

1, 2, & 4

Scope

AURA Bond-World Cup Prep Resurfacing; Group 05 – North Ave NE to Martin Luther King Jr Dr.

Current Budget

$3,929,466.46

Paid

$0.00
Project Start
2024-08-26

Anticipated Design Finish

2025-09-08

Construction Start

2026-03-10
Construction Finish
2026-05-13

Disclaimer: Project schedules and scopes are subject to change.