Safe Streets

Cheshire Bridge Rd

Sidewalks

Type

Sidewalks

Project Number

1091

Council Districts

06

Scope

Includes installation of pedestrian improvements to cross Cheshire Bridge Rd near the intersection of Lenox Rd.

Current Budget

$453,542.00

Paid

$55724.10
Project Start
2019-12-30

Anticipated Design Finish

2021-07-01

Construction Start

2025-09-11
Construction Finish
2026-09-11

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout