Type
Archive
Project number
3050
Council Districts
01

Scope

Action Plan for Safer Streets improvements including a two-way cycle track from Atlanta Ave to Sydney St and bicycle lanes from Sydney St to Woodward Ave. Also includes bus stop boarding areas along Grant Park.

Paid

Project Start

Design Finish

Oct 2020

Construction Start

May 2022

Construction Finish

Oct 2022
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout

Additional Project Information

Project Videos