Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW

Safe Streets

Chapel St SW

Resurfacing

Type

Resurfacing

Project Number

5015

Council Districts

3

Scope

Northside Dr SW to Elliot St

Current Budget

$465,889.93

Paid

$0.00
Project Start
2024-01-08

Anticipated Design Finish

Construction Start

2025-12-01
Construction Finish
2026-01-06

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout