Central Ave Bridge

Bridges

Type

Bridges

Project Number

1020

Council Districts

01, 04

Scope

Includes bridge replacement from Martin Luther King (MLK) Jr Dr to Decatur St. Work includes new street and pedestrian lighting, repair of approaches, signal upgrades, and modification of curbing to create a full lane between Wall St and Decatur St.

Current Budget

$14,048,855.31

Paid

$2854951.39
Project Start
2016-10-17

Anticipated Design Finish

2026-12-31

Construction Start

2027-06-09
Construction Finish
2029-05-29

Disclaimer: Project schedules and scopes are subject to change.